Carpenter and Elms Road
OVERVIEW

INTRODUCTION
The intersection of Carpenter Road and Elms Road was included in the early preliminary engineering phase with support from Flushing Township due to intersection operations and safety concerns. This intersection is included in the 153 intersections that passed the skim analysis for experiencing crashes correctable by a roundabout and is a secondary analysis Tier Two intersection.
During the skim analysis, it was observed that there were 19 angle crashes and 2 head on left turn crashes over the 5-year period. These crashes resulted in 0 fatalities, 1 type A injury, 7 type B injuries, and 20 type C injuries at the intersection.
During the skim analysis, it was observed that there were 19 angle crashes and 2 head on left turn crashes over the 5-year period. These crashes resulted in 0 fatalities, 1 type A injury, 7 type B injuries, and 20 type C injuries at the intersection.
FUTURE NO-BUILD CONDITIONS
The intersection of Carpenter Road and Elms Road is a two-way stop control intersection. Stop signs are present on the Carpenter Road approaches and overhead flashing beacons are present for all approaches. Carpenter Road runs east/west and is a two-lane roadway with one lane in each direction. Elms Road runs north/south and is a two-lane road with one lane in each direction. There is a residence in the southeast quadrant. All other quadrants are currently vacant adjacent to the intersection with the surrounding land use being primarily residential. An aerial of the existing intersection can be seen in the photo above.
An operational analysis of the no-build condition was completed for the intersection using the 2045 forecast traffic volumes. The results of the analysis for future no-build conditions reveals that the Carpenter Road stop-controlled approaches operate at LOS E or F in both the AM and PM peak hours. The Elms Road approaches operate at LOS A in both the AM and PM peak hours
The 95th percentile queue lengths were reviewed at the intersection and results showed that the Carpenter Road approaches experienced a maximum queue length of 330 feet (14 vehicles) during the AM peak hour and 76 feet (4 vehicles) during the PM peak hour.
The operational results for future no-build conditions are presented in the table below.
An operational analysis of the no-build condition was completed for the intersection using the 2045 forecast traffic volumes. The results of the analysis for future no-build conditions reveals that the Carpenter Road stop-controlled approaches operate at LOS E or F in both the AM and PM peak hours. The Elms Road approaches operate at LOS A in both the AM and PM peak hours
The 95th percentile queue lengths were reviewed at the intersection and results showed that the Carpenter Road approaches experienced a maximum queue length of 330 feet (14 vehicles) during the AM peak hour and 76 feet (4 vehicles) during the PM peak hour.
The operational results for future no-build conditions are presented in the table below.

ROUNDABOUT CONDITIONS
A compact,single-lane roundabout with an inscribed circle diameter of 100 feet would improve traffic operations and safety at this intersection. This design would have a fully mountable central island to facilitate truck movements with the smaller diameter. Compact roundabouts have been implemented over the past 5 years at severalsimilar locations in Washtenaw County, Michigan, with positive results. It is likely that a small amount of permanent right-of-way acquisition would be needed in the northwest, southwest, and northeast quadrants of the intersection. An overhead power pole is located in the southeast quadrant and may be impacted by the proposed roundabout. A concept design exhibit for this intersection can be found in the slide above. If desired later in the design process, a standard single-lane roundabout with diameter of 130 feet or greater could be considered at this location. A larger roundabout could result in greater right-of-way impacts and cost.
An operational analysis of the roundabout (build) condition was completed for the intersection using Rodel software and the 2045 forecast traffic volumes. The results of the analysis for roundabout (build) conditions reveal that all approaches and movements at the intersection operate at LOS A during the AM and PM peak hours.
The 95th percentile queue lengths were reviewed, and results showed that all approaches would experience a maximum queue length of 2.9 vehicles during the AM peak hour and PM peak hour for the compact single-lane roundabout design.
The operational results for future roundabout (build) conditions are shown in the table below.
An operational analysis of the roundabout (build) condition was completed for the intersection using Rodel software and the 2045 forecast traffic volumes. The results of the analysis for roundabout (build) conditions reveal that all approaches and movements at the intersection operate at LOS A during the AM and PM peak hours.
The 95th percentile queue lengths were reviewed, and results showed that all approaches would experience a maximum queue length of 2.9 vehicles during the AM peak hour and PM peak hour for the compact single-lane roundabout design.
The operational results for future roundabout (build) conditions are shown in the table below.

RECOMMENDATION
A roundabout appears feasible at this location, assuming GCRC can acquire the limited right-of-way that may be needed.
ROUNDABOUT ESTIMATE
An opinion of probable cost was developed for the compact single-lane roundabout. The probable cost is $1.12 million in year 2025 dollars. This cost includes a 20 percent contingency and 3 percent annual inflation. A full breakdown along with all assumptions can be found in Appendix 3 of the full report below.
Potential funding sources for this improvement could include regular road improvement funding, safety funds, CMAQ, or an earmark. A TOR was computed with a result of 7.30.
For a complete breakdown of the estimate please review the full report below.
Potential funding sources for this improvement could include regular road improvement funding, safety funds, CMAQ, or an earmark. A TOR was computed with a result of 7.30.
For a complete breakdown of the estimate please review the full report below.
FULL REPORT - CARPENTER AND ELMS ROAD
AERIAL VIDEO - CURRENT CONDITIONS
Aerial Video Footage
MODEL SIMULATIONS